TrenchMix brings flood relief

 
trench-mix-brings-flood-relif

Developed in the UK by Bachy Soletanche and Mastenbroek, a TrenchMix machine has been helping to provide flood protection at a site of special scientific interest (SSSI) in Nottingham.

The £650,000 contract forms part of the broader, £51 million Notting-ham Left Bank Flood Alleviation Scheme for the Environment Agency, and provides an economical means of stopping water seeping beneath flood defences.

This work, for main contractor Jackson Civil Engineering and the Environment Agency, uses the patented TrenchMix process, developed jointly by Bachy Soletanche and Mastenbroek.

This involves the construction, below ground, of an impermeable cut-off wall, comprising soil mixed with a binding agent. The technology is a natural development of Bachy Soletanche’s extensive experience in piling and foundations, and is still relatively new in the UK, despite its growing popularity in other parts of Europe.

The Attenborough site is host to a nature reserve. It is important to prevent seepage at the site because the ground is highly permeable and the nature reserve features a number of lakes, hosting many species of water fowl, flora and fauna. This means that, unless preventative measures are taken, the weight of floodwater could drive it underneath the floodwall towards sensitive areas behind the defences.

Environment Agency Midlands director Mark Sitton-Kent said: “We need to create a ‘seepage cut-off’ – an impermeable barrier below ground level to prevent this from happening. The method we chose had to minimise the amount of land we needed to use, reduce disturbance to both people and wildlife, and at the same time be able to work safely alongside high-voltage, electric cables and a major railway line, to the satisfaction of Central Networks and Network Rail.”

He continued: “Initially, because of the ground conditions, the only possible solution seemed to be conventional, hammer-driven sheet piles. TrenchMix offered a new approach. It breaks up and mixes the soil with a cement grout, without the need to excavate and remove it. The resulting mix of soil and grout solidifies to form a continuous underground barrier, preventing high flood levels driving water through the ground beneath the flood wall, and protecting the areas behind the defences.”

The area flood risk manager, Innes Thomson, said: “TrenchMix offers significant benefits. It is faster than conventional sheet-piling machines, uses low-height equipment, and its lower noise and vibration levels will reduce disturbance to wildlife, visitors and local residents. We will also need to use less land to build the defence, and any earth excavated can be recycled on site for landscaping work. This will result in less traffic on local roads.”

In addition to the specialised equipment provided by Mastenbroek, the TrenchMix process relies on a rigorous specification and detailed procedures drawn up by Bachy Soletanche to construct continuous, impervious walls for foundations or leachate cut-off applications.

The 400mm-thick barrier offers a permeability better than 1x10-8m/s and a compressive strength greater than 0.5MPa. Much higher strengths are achievable, depending on the ground conditions and slurry design.

TrenchMix uses a Mastenbroek trencher, which is similar in appearance to those used for land drainage, but the action of the chain is reversed to facilitate the mixing of slurry below ground. The arisings at the surface are kept to a minimum and in some cases there are none.

The trencher, with its long boom, is highly manoeuvrable and capable of operating within a narrow corridor, as at Nottingham, with its adjacent railway track.

The only raw material required is cementitious grout. At the Notting-ham site this is very cementitious, containing no bentonite or similar materials. The water required to mix with the grout is taken from the adjacent lake, reducing transport costs and the use of potable water.

Grout is injected at a controlled rate into the soil. It does not flow away, but is moved by the direct mixing action of the boom and mixing teeth, and rapidly worked into the soil, forming a stiff material, retained in shape by the undisturbed adjacent ground. This material sets within hours.
Courtesy Geo Drilling

 

 